   9.1. General information
   9.2. Check of antisplash covers
   9.3. Removal and installation of the drive of forward wheels
   9.4. Removal and installation of the internal hinge
   9.5. Removal and installation of the external hinge
   9.6. Dismantling of the external hinge
   9.7. Dismantling of the internal hinge
   9.8. Quencher of tortional fluctuations of a power shaft
   9.9. Half shaft flange epiploon
   9.10. Malfunctions of power shafts
+ 10. Suspension brackets
+ 11. Steering
+ 12. Brake system
+ 13. Wheels and tires
+ 14. Systems of heating, ventilation and conditioning
+ 15. Electric equipment
+ 16. Body
+ 17. Electric circuits



ed639308




Repair Volkswagen Passat B3-B4/Passat B3-B4>> Drive of forward wheels>> Dismantling of the internal hinge
As spare parts to the hinge antisplash covers, washers, lubricant, a nut of a power shaft and spring lock rings are delivered.
You carry out dismantling of the internal hinge in the following order:

Fig. 9.13. Extraction of spheres from a nave


Fig. 9.16. Extraction of a nave with a separator from the case of the external hinge


– turn a nave with a separator and take them from the hinge case (see fig. 9.13 ). Take spheres from a separator. To take a nave from a separator, turn a nave in a separator so that paths of spheres settled down parallel to an end face of a nave (fig. 9.16) ;
– clear all details of the hinge and check their state. If there are wear tracks or corrosion, replace the hinge assembled.
You carry out assembly of the internal hinge in the following order:

Fig. 9.17. Installation of spheres in a separator of the internal hinge


– insert a nave into a separator, having performed operations in the sequence, the return to its extraction, then insert spheres (fig. 9.17) into a separator ;

Fig. 9.18. At installation of a nave in the case the bigger distance on the case(s) would have to be combined with a nave bottleneck


– establish a nave at an angle 90 ° to the case and check that the bigger distance on the case was combined with a nave bottleneck then turn a nave and install it in the case of the hinge (fig. 9.18, 9.19) ;

Fig. 9.19. The correct turn of a nave, for its installation in the case


Fig. 9.20. The place of pressing a separator for installation of spheres in the hinge case


– be convinced that the flute on an internal surface of a nave is directed to the bigger diameter of the case of the hinge. Turn a nave from a separator that spheres entered flutes in the case, then press a separator so that the nave and spheres were established into place in the case of the hinge (fig. 9.20) ;
– move manually a hinge nave in different directions to check smoothness of movement and correctness of assembly.